Hudson Companies of Hermitage, PA proposes to build a new 10-story apartment building at 419 Melwood Avenue in North Oakland. Plans include apartments ranging in size from micro to two bedrooms and an indoor parking garage with 93 spaces for automobiles and 68 bicycles.
A representative from Hudson presented the plans for a 128-unit building at the April 27, 2021 Oakland-Wide meeting.
Responding to a resident’s inquiry following the meeting concerning potential detrimental impacts on traffic patterns and residential compatibility standards of the zoning code (see comments section below), Zoning Development Review staff (including DOMI) commented:
A Zoning and Development Review Application has not yet been made, but based on our understanding of the proposed scope, a new apartment building in a UI / Baum Centre Overlay zoning district will require Planning Commission review and approval and a ZBA Hearing for a Special Exception for Use.
Until a formal ZDR application is made, it's unclear if additional Special Exceptions or Variances will be required per Residential Compatibility Standards or 904.07.C.4 - Special Exception for Height in the UI.
DOMI will also require a transportation study to clarify the project's impact on the right-of-way.
OPDC hosted a follow-up meeting with the developers and representatives from the Department of City Planning, Councilman Lavelle’s office, and bordering community groups to discuss traffic and parking concerns on May 19, 2021. Notes from the meeting are linked below.
Hudson Companies presented at the Zoning Board of Adjustment (ZBA) on July 8, 2021. The project is now listed as a 10-story, 148-unit development. Gateway Engineers prepared a traffic study in July; the memo is located in “Resources” below.
The ZBA approved Hudson Companies’ request for special exceptions to construct a 10story/116’ tall building with an 8.4:1 FAR. (9/13/21)
The project went before the Planning Commission for a hearing on December 7. Planning approved the building; demolition and construction are planned to start in early 2022.
Resources:
Memo from Hudson Companies to OPDC re: building information changes (June 30, 2021)
Updated design (as of June 30, 2021)
OPDC’s July 7, 2021 letter to the Zoning Board of Adjustment
September 13, 2021 - ZBA’s decision re: July 8, 2021 meeting